On this page:

About RIT-Ts

VicGrid conducts regulatory investment tests for transmission (RIT-T) on potential transmission network and non-network projects.

The purpose of the RIT-T, as set out at clause 5.16 of the electricity Rules, is to identify the credible option that maximises the present value of net economic benefit to all those who produce, consume and transport electricity in the market.

The RIT-T process is a regulatory mechanism that applies an economic cost-benefit test to identify the preferred investment to meet an identified need.

When not an actionable Integrated System Plan project, the RIT-T process requires the RIT-T proponent considering an investment to publish 3 reports:

  1. The Project specification consultation report (PSCR) seeks feedback and advice on the identified need to invest and credible options to be assessed.
  2. The Project assessment draft report (PADR) identifies and seeks feedback on the assessment approach and proposed preferred option, considering submissions to the PSCR consultation process.
  3. The Project assessment conclusions report (PACR) presents the RIT-T proponent’s preferred solution, considering submissions to the PADR, which is the credible option that maximises the present value of net economic benefit to all those who produce, consume and transport electricity in the national electricity market.

Update on regulatory tests

In-progress RIT-Ts

There are currently no RIT-T's in progress.

Cancelled/discontinued RIT-Ts

The Western Metropolitan Melbourne Reinforcement and Eastern Victoria Grid Reinforcement RIT-Ts will not proceed further as standalone regulatory assessments.

Investment decisions for the projects originally identified under these RIT-Ts have now been integrated into the 2025 Victorian Transmission Plan (VTP) priority programs.

The Western Metropolitan Melbourne Reinforcement RIT-T was initiated to address thermal limitations and supply reliability in western metropolitan Melbourne and Geelong. The PSCR was published in March 2025.

The Eastern Victoria Grid Reinforcement RIT-T was initiated to resolve thermal limitations of 220 kV lines and 500/220 kV transformers used to supply the eastern metropolitan Melbourne area. The PSCR was published in November 2024.

Under the standard National Electricity Rules (NER) process, these projects would typically proceed to a PADR, however, the introduction of Victorian Transmission Investment Framework (VTIF) has facilitated a more coordinated, long-term approach through the VTP.

Delivery of these critical infrastructure upgrades will now occur through the VTP priority programs and VicGrid will continue to monitor Victorian network needs and progress future requirements through its ongoing strategic planning processes.

Completed RIT-Ts

Page last updated: 13/10/26