The optional pre-feasibility stage
The National Electricity Rules (NER) do not require connection applicants to follow this stage, however we encourage you to explore the feasibility of your project, begin discussion with the VicGrid Connections team, landowners and relevant government authorities during the initial stages of development.
VicGrid can provide applicants with information about connections, including:
- explanation of the connection process and the regulatory framework
- indicative timeline and cost for the connection of your project
- high-level technical information
- information that may be useful when evaluating your connection location
- to provide necessary transmission network data upon request. For more information, visit our Data provision page.
You should discuss with us the proposed location of your installation and where you would like to connect to the transmission network. You should also explore land and land-use planning implications to avoid delays.