The application stage

Submitting an application to connect initiates key activities in the connection process. Connection applicants should submit their application to VicGrid Connections, together with all required supporting information.

This typically includes:

  • completed Connection application form
  • proposed switching arrangement for connection to the Declared Shared Network (DSN)
  • the location of the proposed connection point
  • Proposed Performance Standards – completed Customer Performance Standards template
  • description of the proposed installation, including data requirements outlined in the Schedules 5.4 and 5.5 of National Electricity Rules (NER)
  • model package, including simulation models and associated design data (see the AEMO Modelling requirements page for more details on the data and model packages required)
  • project and commissioning programs
  • any other requirements stipulated in the enquiry response.

The proposed Performance Standards must be consistent with the Access Standards detailed in the relevant Schedules of Chapter 5 of the Rules.

We will advise you of the additional information required before the application can be processed. The requirements of a complete application are covered in the Customer Connection Application Checklist.

We will assess the application to connect together with the proposed Performance Standards. If required, the Generator connection application checklist can be found on the AEMO website.

Once reviewed, we will notify you of our approval to the Performance Standards (clause 5.3.4A) and the outcome of the System Strength Impact Assessment with any requirement for System Strength Remediation (clause 5.3.4B).

We will also assess the need for network augmentations and their contestability.

Next stage

Page last updated: 29/10/25